Assembly and testing technology

Assembly line for front modules

Assembly line for automatic bolting of front modules. The pre-assembled modules are loaded by hand using a manipulator. Both pneumatic and electrical bolting occurs automatically with inspection of the torques achieved. The robot removes and puts the modules into the automated test equipment. Afterwards, they are placed onto a discharge belt.


Leiter Projektmanagement
Karl Aich
Phone: +49 9421 739 - 285
Fax: +49 9421 739 - 6285

Technical Data

Cycle time “Series 164” 84 sec.

Cycle time “Series 251” 115 sec.

Design of the assembly line acc. to US – Standard

Location Tuscaloosa, Alabama, USA

Availability 95 %

Highlights

Parallel production of two different products (Series 164 and Series 251)

100% inspection of bolted front modules; in case of NOK discharge and rework

Afterwards, feeding before automated test equipment thus ensuring the 100% inspection.


Assembly line for front modules

Assembly line for automatic bolting of front modules. Loading of the preassembled modules is made by hand with the aid of a manipulator. Both pneumatic and electrical bolting is made automatically with inspection of the torques obtained. Modules are taken by the robot and deposited into the test equipment. Afterwards they will be deposited onto a discharging belt.


Leiter Projektmanagement
Karl Aich
Phone: +49 9421 739 - 285
Fax: +49 9421 739 - 6285

Technical Data

Cycle time "Series 164" 84 sec

Cycle time "Series 251" 115 sec

Equipment design acc. to US Standard

Site Tuscaloosa, Alabama, USA

Availability 95 %

Highlights

Parallel production of two different products (Series 164 and Series 251)

100% inspection of bolted front modules; in case of NOK discharging and reworking

Afterwards charging in front of the test equipment. Thus the 100% inspection will continue to be ensured